Renovation Project Updates

August 8, 2026

WE ARE MOVING FORWARD!

August 1-8: with a group of amazing volunteers, we are right on schedule!

Here's what is happening:

We have packed up all the adult non-fiction books, the biography section, the DVDs and audiobooks, and started on adult fiction. 

During our scheduled volunteer hours this first week, 16 kids and 21 adults filled up 292 boxes and disassembled 245 shelves!

Currently:

We still have the kids' playroom open, and computer use, printing, faxing services continue. The Press News Journal and the Wall Street Journal is still here for you to enjoy. 

Next: 

We are continuing with boxing up the adult fiction section in the beginning of next week (starting on August 10), then moving on to large print books and the young adult section.

If you are looking to read any ADULT FICTION, LARGE PRINT, or YA materials, come and grab your books now! Kids books will be next!

July 10, 2026

Scheduled phases of the renovation project

August 1-21: boxing up books and supplies, disassembling shelving.

August 22: loading boxes and furniture onto semi trailers (thank you, Andrew Eisenbeiss for the trailers and Culver-Stockton EDM Day Students for the heavy lifting!)

August 23-31: removal of remaining items, and final preparations for renovations

August 29: LIBRARY CLOSES - see your options for accessing library services here

September 1: asbestos removal begins

Mid-September: interior painting and flooring installation begins

Late-September: books and materials begin returning to the library, shelving assembled

October: LIBRARY OPENS